10/4/2024
We are thrilled to share updates on our Lagoon Remediation Project facilitated by Our Katahdin and One North. This significant project, aimed at repurposing the lagoons and the future site of Great Northern Salmon’s (GNS), is backed by a dedicated team of financing partners, including the U.S. EPA Brownfields, Maine DEP Brownfields, Maine DECD, NBRC, EMDC, and GNS.
Staging activities began in mid-September, with site preparation and dredging kicking off in late September. The project is progressing rapidly, and we anticipate that phase one of the remediation will be completed by early to mid-December, in timer the planned for the planned suspension during the freeze-up months.
Looking ahead, phase two of the remediation projects set to commence in early Spring, with the entire remediation project expected to conclude by summer 2025. At that point, Great Northern Salmon’s construction phase will begin.